Alnatura Logistics Center

The Alnatura Logistics Center in Lorsch consists of a logistics hall covering approximately 20,800 m², a 650 m² two-story office building, a 9,360 m² high-bay warehouse, and a 120 m² quarantine warehouse.

The project was completed in two construction phases. The administration building, storage areas, and order-picking hall are arranged to keep travel distances between the various areas as short as possible while ensuring that future extensions will not disrupt operations. Added during the second construction phase, the high-bay warehouse provides approximately 25,000 pallet spaces and accommodates the entire reserve stock for the order-picking hall.

ProjectAlnatura Logistics Center Lorsch

LocationGewerbegebiet Lorsch

Statusfertiggestellt 2014

BGF31.510 m²

Baukosten13.25 Mio. € netto

Service phases1-5

Photography© Norman A. Müller, Ingolstadt
© BFK Architekten

DGNB 2011Detail Bauband 304, Umhüllen und Konstruieren 2015